June, 2022
First shell completion
The shell of house 5 will be completed within the next 3 weeks — this will be the first completed shell of the project, the finishing work will begin subsequently. The other houses of the project will be completed successively. Of the planned shell volume of the project, a total of approx. 60% has been completed.
April, 2022
Backfilling
In houses 4 and 5 the shell is on the 2nd floor, while in houses 1 and 2 the basement and the first floor are almost finished. In house 3, the floor slab is being constructed. Backfilling work is now starting in the area of the excavation pits. Overall, the construction work is progressing in great strides.
February, 2022
Shell construction
The shell construction of houses 4 and 5 is progressing rapidly. Some of the exterior walls on the first floor are already being built. In the excavation pit of houses 1, 2 and 3, the foundation slab is being completed.
January, 2022
Progress H4 & H5
In the excavation pit of houses 4 and 5, the structural work on the basement is currently underway — the walls are currently being erected.
January, 2022
Progress H1 & H2
The excavation pit for houses 1 and 2 has now been completely dug. In house 2, steel reinforcements are already being inserted for the foundation, while in House 1 the ground is still being leveled.