Look for your new home
in “Am Park” at Potsdam

rooms
level
reset
apply changes
1.0.0168,65 m²592.734,00 €PDF
1.0.0454,09 m²562.449,00 €PDF
2.0.00*119,45 m²731.504,00 €PDF
2.0.0197,62 m²814.998,00 €PDF
2.0.0275,46 m²569.336,00 €PDF
2.1.03144,26 m²1.047.861,00 €PDF
2.1.0575,08 m²529.697,00 €PDF
2.2.0875,02 m²570.228,00 €PDF
2.3.09150,53 m²1.299.020,00 €PDF
2.3.1175,06 m²629.734,00 €PDF
3.0.0176,04 m²582.347,00 €PDF
3.0.0297,55 m²818.377,00 €PDF
3.2.0694,18 m²743.663,00 €PDF
3.2.08126,80 m²978.155,00 €PDF
3.3.0994,24 m²804.606,00 €PDF
3.3.11131,88 m²1.142.104,00 €PDF
4.0.0269,46 m²639.371,00 €PDF
4.0.0568,65 m²612.491,00 €PDF
4.1.0878,05 m²592.754,00 €PDF
4.1.1068,69 m²541.178,00 €PDF
4.2.1268,69 m²539.396,00 €PDF
4.2.1568,69 m²587.751,00 €PDF
4.3.1678,49 m²748.958,00 €PDF
5.0.0168,36 m²676.709,00 €PDF
5.0.0236,76 m²360.654,00 €PDF
5.0.0332,16 m²327.178,00 €PDF
5.0.0431,94 m²309.048,00 €PDF
5.0.0536,76 m²309.048,00 €PDF
5.0.0668,36 m²570.911,00 €PDF
5.2.1967,60 m²567.909,00 €PDF
5.3.2227,11 m²294.478,00 €PDF
5.3.2327,05 m²284.084,00 €PDF
5.3.2431,04 m²314.371,00 €PDF

© 2021 Dia­mo­na & Harnisch.
Leip­zi­ger Platz 14, 10117 Berlin-Germany

Slide
June, 2022

First shell completion

The shell of house 5 will be completed within the next 3 weeks — this will be the first completed shell of the project, the finishing work will begin subsequently. The other houses of the project will be completed successively. Of the planned shell volume of the project, a total of approx. 60% has been completed.

April, 2022

Backfilling

In houses 4 and 5 the shell is on the 2nd floor, while in houses 1 and 2 the basement and the first floor are almost finished. In house 3, the floor slab is being constructed. Backfilling work is now starting in the area of the excavation pits. Overall, the construction work is progressing in great strides.

February, 2022

Shell construction

The shell construction of houses 4 and 5 is progressing rapidly. Some of the exterior walls on the first floor are already being built. In the excavation pit of houses 1, 2 and 3, the foundation slab is being completed.

January, 2022

Progress H4 & H5

In the excavation pit of houses 4 and 5, the structural work on the basement is currently underway — the walls are currently being erected.

January, 2022

Progress H1 & H2

The exca­va­ti­on pit for houses 1 and 2 has now been com­ple­te­ly dug. In house 2, steel rein­for­ce­ments are alrea­dy being inser­ted for the foun­da­ti­on, while in House 1 the ground is still being leveled.

December, 2021

Excavations

The excavations are progressing. In two of the five excavation pits, concreting of the floor slab has already begun, while preparatory earthworks are underway in the remaining areas.

Die Umsetzung von Gestaltungsvorschlägen, Planungsunterlagen und dargestellten 3-D-Visualisierungen der Gebäude und einzelner Räume in dieser Broschüre können von der Realität und der tatsächlichen Ausführung, auch hinsichtlich der Flächenangaben, abweichen. Vorgestellte Materialien, Fabrikate und Ausstattungsgegenstände sind ein unverbindlicher Gestaltungsvorschlag und können gegebenenfalls variieren. Aufwertende Ausstattung / Upgrades sind gegen Aufpreis selbstverständlich möglich. Verbindlich für die Ausführung sind allein die Bau - und Leistungsbeschreibung des Kaufvertrages. Abweichungen aufgrund behördlicher Auflagen und Änderungen durch die Genehmigungsbehörden bleiben vorbehalten.