June, 2023
Facade completion
The interior plaster and screed works are completed. Currently, the last works on the facade are in progress and will be finished by the end of July. The interior finishing work is progressing rapidly — the tiling, parquet and painting trades are working in the various houses. The outdoor facilities are also currently being prepared.
MARCH, 2023
Interiors
The project is progressing with great strides. In House 5, the parquet and tiling work is currently underway. The building services are fully completed. House 4 and 1 are currently undergoing scaffolding work. Almost 70% of the interior plastering and screed work has been completed.
December, 2022
Facade completion
The scaffolding of house 5 will be dismantled in January after completion of the facade. Then the other houses will be completed successively at intervals of 4–6 weeks. In house 5, the TGA installations, the drywall construction as well as the plastering and screed work will be completed — the other houses will follow according to construction progress. The exterior works will start in the second half of February.
JULY, 2022
SHELL CONSTRUCTION PROGRESS
The shell of houses 4 and 5 is completed, currently the windows are being installed. The completion of house 3 will follow at the end of August. ETICS insulation on houses 4 and 5 is now commencing, drywall construction is already progressing rapidly.
June, 2022
First shell completion
The shell of house 5 will be completed within the next 3 weeks — this will be the first completed shell of the project, the finishing work will begin subsequently. The other houses of the project will be completed successively. Of the planned shell volume of the project, a total of approx. 60% has been completed.
April, 2022
Backfilling
In houses 4 and 5 the shell is on the 2nd floor, while in houses 1 and 2 the basement and the first floor are almost finished. In house 3, the floor slab is being constructed. Backfilling work is now starting in the area of the excavation pits. Overall, the construction work is progressing in great strides.
February, 2022
Shell construction
The shell construction of houses 4 and 5 is progressing rapidly. Some of the exterior walls on the first floor are already being built. In the excavation pit of houses 1, 2 and 3, the foundation slab is being completed.
January, 2022
Progress H4 & H5
In the excavation pit of houses 4 and 5, the structural work on the basement is currently underway — the walls are currently being erected.
January, 2022
Progress H1 & H2
The excavation pit for houses 1 and 2 has now been completely dug. In house 2, steel reinforcements are already being inserted for the foundation, while in House 1 the ground is still being leveled.